Works are anticipated
to take 2 – 3 weeks to complete, consisting of 3 days planing off existing
surface, 3-4 days installing kerb edgings, 2 days digging out and making good
softer areas, 3-4 days surfacing. The working area is to be fenced off entirely
using temporary security fencing for the duration of works, this includes
fencing down to the water’s edge to ensure no pedestrians can gain access to
the working area.
The pedestrian footpath running
alongside the road will be closed for the first 3 days during planing and then
re-opened.